J-26-1661
Invoiced Supply only their PO GAS73721Supply — overhead exhaust rail system, 6 m
To pick → Picked → Awaiting stock → Despatched → Complete Invoiced Completed 09 July 2025
Lines
Priced off Gas & Supplies WA's agreement. Margin is against landed cost.
| Code | Description | Qty | Unit | Amount | Cost | Margin | Issued |
|---|---|---|---|---|---|---|---|
| VE-RAIL-6 | Overhead exhaust rail system, 6 m (Platinum 31%) | 2 ea | $8,970.00 | $17,940.00 | $17,127.60 | 5% | Issued |
| DCT-FLG-200 | Flange ring Ø200, drilled (Platinum 15%) | 3 ea | $55.25 | $165.75 | $102.12 | 38% | Issued |
| DCT-SDL-315 | Saddle take-off Ø315 (Platinum 15%) | 5 ea | $131.75 | $658.75 | $428.10 | 35% | Issued |
| DCT-SPG-500 | Spigot Ø500, flanged (Platinum 15%) | 10 ea | $199.75 | $1,997.50 | $1,270.50 | 36% | Issued |
| FRT-METRO | Delivery, Perth metro (Platinum 15%) | 1 ea | $72.25 | $72.25 | $65.00 | 10% | n/a |
| Subtotal ex GST | $20,834.25 | ||||||
| GST 10% | $2,083.43 | ||||||
| Total inc GST | $22,917.68 | ||||||
Where the money went
Sell, ex GST$20,834.25
Parts at landed cost$18,993.32
Hours booked · 0 h $0.00
Gross margin $1,840.93 · 8.8%
Customer & site
Bibra Lake — main site
Bibra Lake WA · Perth metro
Raised 24 June 2025 by Zac Albert. Sold by Zac Albert · Followmont CN739327.
Hours booked
The half of job cost a supplier invoice never shows.
No hours booked against this job yet.
Stock issued
| Code | Qty | When |
|---|---|---|
| VE-RAIL-6 | -2 | 09 July 2025 |
| DCT-SPG-500 | -10 | 09 July 2025 |
| DCT-SDL-315 | -5 | 09 July 2025 |
| DCT-FLG-200 | -3 | 09 July 2025 |
Book hours
Goes straight onto job margin.