J-26-1726 Demo Fortescue Port Hedland Operations · Port Hedland — main site
5 agency brands MYOB · synced 9:14 am 08 Oct 2026

J-26-1726

Despatched Supply, install & electrical

Supply, install and electrical — aer201 portable fume extractor

To pick → Picked → Awaiting stock → Despatched → Complete Invoiced Scheduled 24 Aug 2026 · 45 days ago

Lines

Priced off Fortescue Port Hedland Operations's agreement. Margin is against landed cost.

CodeDescriptionQtyUnitAmountCostMarginIssued
FE-AER201 AER201 portable fume extractor (Gold 23%) 1 ea $4,389.00 $4,389.00 $3,306.76 25% Issued
Supply, install and electrical — turnkey, per scope letter (Written in) 1 $14,500.00 $14,500.00 $9,482.00 35% On the shelf
Aerovent spare impeller — part number to be confirmed with Bayswater (Written in) 1 $620.00 $620.00 $420.00 32% On the shelf
Electrical installation — isolators, cabling and connection by others (Written in) 1 $4,300.00 $4,300.00 $2,921.20 32% On the shelf
LAB-INSTALL Installation, supply and fit (Gold 11%) 16 h $129.05 $2,064.80 $992.00 52% n/a
LAB-TRAVEL Travel, Perth metro (Gold 11%) 13 h $97.90 $1,272.70 $702.00 45% n/a
Freight, regional$425.00
Subtotal ex GST$27,571.50
GST 10%$2,757.15
Total inc GST$30,328.65

Where the money went

Sell, ex GST$27,571.50
Parts at landed cost$17,823.96
Hours booked · 0 h $0.00
Gross margin $9,747.54 · 35.4%
29 h was quoted, 0 h has been booked. 29 h under.

Customer & site

Fortescue Port Hedland Operations
Lisa Prendergast · (08) 9386 8005
45 days EOM · Gold
Port Hedland — main site
Port Hedland WA · Pilbara
Before you go: Full site induction required
Raised 05 Aug 2026 by Nicola Rock. Sold by Nicola Rock · Centurion CN862511.

Hours booked

The half of job cost a supplier invoice never shows.

No hours booked against this job yet.

Stock issued

CodeQtyWhen
FE-AER201 -1 09 Aug 2026