J-26-1656
Invoiced Supply, install & electrical their PO CSB65365Supply, install and electrical — jetblack bh03 personnel cleaning booth, powder coated
To pick → Picked → Awaiting stock → Despatched → Complete Invoiced Completed 30 May 2025
Lines
Priced off CSBP Limited's agreement. Margin is against landed cost.
| Code | Description | Qty | Unit | Amount | Cost | Margin | Issued |
|---|---|---|---|---|---|---|---|
| PC-BH03-POWD | JetBlack BH03 personnel cleaning booth, powder coated (Gold 20%) | 2 ea | $13,880.00 | $27,760.00 | $23,565.80 | 15% | Issued |
| Aerovent axial fan package, ex Melbourne — freight included (Written in) | 1 | $2,650.00 | $2,650.00 | $1,692.60 | 36% | On the shelf | |
| Ductwork modification on site — labour and materials (Written in) | 1 | $2,550.00 | $2,550.00 | $1,596.00 | 37% | On the shelf | |
| LAB-INSTALL | Installation, supply and fit (Gold 11%) | 14 h | $129.05 | $1,806.70 | $868.00 | 52% | n/a |
| Subtotal ex GST | $34,766.70 | ||||||
| GST 10% | $3,476.67 | ||||||
| Total inc GST | $38,243.37 | ||||||
Where the money went
Sell, ex GST$34,766.70
Parts at landed cost$27,722.40
Hours booked · 18 h $1,116.00
Gross margin $5,928.30 · 17.1%
14 h was quoted, 18 h has been booked.
That is 4 h over — it comes straight off this margin.
Customer & site
Kwinana AN plant — change house
Kwinana Beach WA · Perth metro
Before you go: CSBP full site induction, 2 days
Raised 26 May 2025 by Zac Albert. Sold by Zac Albert · Followmont CN752313.
Hours booked
The half of job cost a supplier invoice never shows.
| Date | Who | What | Hours | At cost | Charged | Notes |
|---|---|---|---|---|---|---|
| 29 May 2025 | Zac Albert | Install | 6 h | $372.00 | $870.00 | |
| 30 May 2025 | Zac Albert | Install | 12 h | $744.00 | $1,740.00 | |
| Total | 18 h | $1,116.00 | $2,610.00 | |||
Stock issued
| Code | Qty | When |
|---|---|---|
| PC-BH03-POWD | -2 | 30 May 2025 |
Book hours
Goes straight onto job margin.