J-26-1704
Invoiced Supply, install & electrical their PO WCO44478Supply, install and electrical — evo 3.2 welding fume extractor, 4 m arm, 3ph
To pick → Picked → Awaiting stock → Despatched → Complete Invoiced Completed 09 July 2026
Lines
Priced off Water Corporation's agreement. Margin is against landed cost.
| Code | Description | Qty | Unit | Amount | Cost | Margin | Issued |
|---|---|---|---|---|---|---|---|
| FE-EVO32-4M-3PH | EVO 3.2 welding fume extractor, 4 m arm, 3PH (Silver 15%) | 1 ea | $9,732.50 | $9,732.50 | $7,219.57 | 26% | Issued |
| Aerovent axial fan package, ex Melbourne — freight included (Written in) | 1 | $2,850.00 | $2,850.00 | $1,874.60 | 34% | On the shelf | |
| Crane hire and rigging, half day (Written in) | 1 | $1,550.00 | $1,550.00 | $1,262.60 | 19% | On the shelf | |
| LAB-INSTALL | Installation, supply and fit (Silver 7.5%) | 28 h | $134.13 | $3,755.64 | $1,736.00 | 54% | n/a |
| Subtotal ex GST | $17,888.14 | ||||||
| GST 10% | $1,788.81 | ||||||
| Total inc GST | $19,676.95 | ||||||
Where the money went
Sell, ex GST$17,888.14
Parts at landed cost$12,092.77
Hours booked · 24 h $1,488.00
Gross margin $4,307.37 · 24.1%
28 h was quoted, 24 h has been booked.
4 h under.
Customer & site
Balcatta water treatment workshop
Balcatta WA · Perth metro
Before you go: Water Corp contractor induction
Raised 06 July 2026 by Zac Albert. Sold by Zac Albert · Own ute CN486845.
Hours booked
The half of job cost a supplier invoice never shows.
| Date | Who | What | Hours | At cost | Charged | Notes |
|---|---|---|---|---|---|---|
| 07 July 2026 | Zac Albert | Install | 4 h | $248.00 | $580.00 | |
| 08 July 2026 | Zac Albert | Install | 8 h | $496.00 | $1,160.00 | |
| 09 July 2026 | Zac Albert | Install | 12 h | $744.00 | $1,740.00 | |
| Total | 24 h | $1,488.00 | $3,480.00 | |||
Stock issued
| Code | Qty | When |
|---|---|---|
| FE-EVO32-4M-3PH | -1 | 09 July 2026 |
Book hours
Goes straight onto job margin.